Delivery date of car and passenger ferry Aurora Botnia, operating between Vaasa in Finland and Umeå in Sweden, moved to July

The car and passenger ferry Aurora Botnia is nearing the end of the construction phase at Rauma Marine Constructions’ shipyard in Rauma, Finland and will be handed over to Wasaline in mid-July this year. The adjusted date of handover in July allows RMC enough time for the preparatory work done on the ferry’s innovative fuel solution to be completed and to assure a corona-safe working environment at the shipyard.

Last week, Aurora Botnia completed its first sea trial and performance tests. After the successful sea trial, the RMC shipyard has been preparing for the next sea trial that will concentrate on testing the ship’s primary fuel, liquefied natural gas (LNG).

With further preparatory work for the second sea trial required, Aurora Botnia’s delivery schedule has also been adjusted.

“This is a new generation car and passenger ferry that can use LNG, electricity, and in the future, biogas as fuel. Preparatory work for the innovative fuel solution has taken more time than expected, which has resulted in an adjusted delivery date for July,” says Jyrki Heinimaa, CEO, Rauma Marine Constructions.

According to Heinimaa, it is also very important that the final phase of construction work can be handled in a way that is as corona-safe as possible.

“Together with the customer, in March, we already decided that the most important thing is to keep the number of people finishing and commissioning the ship within corona-safe limits. We have succeeded in this, and the coronavirus situation at the shipyard has remained calm. With the July handover schedule, we will be able to continue working to ensure that the ship is handed over without compromising safety.”